Completing the management of the progress of the Bung River 4 - 2 hydropower project


ODA : Official Development Assistance (Official Development Assistance) OCR : Ordinary Credit Resources


LIST OF TABLES

Table 2.1 Capital plan table for implementing Song Bung 4 Hydropower project 31

Maybe you are interested!

Table 2.2 Group 32 reporting regulations

Table 2.3 Reporting regulations of the Ministry of Planning and Investment 33

Completing the management of the progress of the Bung River 4 - 2 hydropower project

Table 2.4 ADB reporting requirements 33

Table 2.5 Assessment of key progress milestones from 2008-2010 37

Table 2.6 Summary of bidding plan for 2006-2010 45

Table 2.7 Summary of bidding packages by fields and forms of contractor selection in 2006-2010 48

Table 2.8 Percentage of Project Progress 56

Table 3.1 Criteria to be monitored 61

Table 3.2 Monitoring report based on approved plan 62

Category: Management and operation area of ​​Song Bung 4 Hydropower Plant 62

Table 3.3. Progress report of Song Bung 4 Hydropower project 67

Table 3.4 Data table measuring the fluctuations of the plan from 2008 to 2010 70

Table 3.5 Identifying project roles on the responsibility diagram using abbreviations 77

Table 3.6 Using decisions in the responsibility diagram 78

Table 3.7. Responsibility diagram for key project milestones 81

Table 3.8 Communication plan for project team in 2010 82

Table 3.9 Communication Plan for ADB 2010 82

Table 3.10 Communication plan for project affected people in 2010 83


LIST OF FIGURES AND GRAPHICS


Figure 1.1 Project Management Process 7

Figure 1.2 Gantt chart for the normal program of project M 9

Figure 1.3. Network diagram of project Z according to AOA method 11

Figure 1.4. Analysis of income value 15

Figure 1.5 Graphical representation of the variations in EVA costs and usage time. 16 Figure 1.6. Table of Contents 19

Figure 1.7. Project Progress Trend Forecast 20

Figure 2.1 Progress plan of Song Bung 4 Hydropower Project 30

Figure 2.2 Progress of Song Bung 4 Hydropower Project 36

Figure 2.3 Overall project progress after adjustment 40

Figure 3.1 Chart showing the weights of the main categories 65

Figure 3.2 Chart showing the weights of the main categories 66

Figure 3.3 Progress control system 69

Figure 3.4a Fishbone diagram identifying the cause of the delay in the progress of the operation management building 71

Figure 3.4b Fishbone diagram identifying the cause of the delay in the progress of the operation management building 72

Figure 3.4c Fishbone diagram identifying the cause of the delay in progress of the 72 operations management building

Figure 3.5 Responsibility diagram 76


INTRODUCTION


1. Urgency of the topic

Quang Nam is one of the early provinces to develop hydropower in the Central Highlands region. Many hydropower plants have been put into operation, supplementing the national electricity supply, contributing significantly to solving the increasing shortage of electricity nationwide, contributing to increasing the value of industrial production, creating a stable source of income for the local budget and will have additional revenue from the hydropower benefit sharing fund to invest in improving the lives of people in affected areas, contributing to promoting socio-economic development and creating a new look for the mountainous districts of Quang Nam province.

Vietnam Electricity Group (EVN) is investing in 19 hydropower projects and 8 thermal power projects. Although it has actively coordinated with consulting agencies and construction contractors to simultaneously implement projects, and construction units have made many efforts and proactively coordinated construction direction to complete the annual plan, there are still some projects that are not on schedule.

Specifically, the A Vuong hydropower project, which started in 2003, was expected to generate electricity for unit 1 at the end of 2007 and be completed in 2008, but in the flood season of 2006, the construction site suffered severe consequences from two storms No. 6 and No. 9 that hit Quang Nam and Da Nang, causing heavy rain and floods (exceeding the designed flood frequency), so some construction items could not withstand the flood, so this project may generate electricity for unit 1 in the fourth quarter of 2008. The Tuyen Quang hydropower project, which started in 2002, was expected to generate electricity for unit 1 at the end of 2006, but due to the EPC General Contractor signing the contract for the electromechanical equipment supply package late, the progress of generating electricity for unit 1 had to be delayed to August 2007.

Song Bung 4 Hydropower Project is the first hydropower project that the Asian Development Bank has facilitated to arrange funding for the project under the cooperation program between the Vietnamese Government and the Asian Development Bank. During the project implementation in general and the project progress management in particular,


In particular, some items of the project are also not beyond the possibility of this delay. Some of the biggest difficulties and obstacles come from the application of progress management techniques in planning, project supervision & control and the influence of project participants. In addition, the preparation and approval of the Technical Design and Total Estimate for some items of the project is slower than required; Domestic consulting capacity is still limited; Bidding and selection of construction contractors do not meet the schedule and are not synchronous; Some difficulties in compensation and site clearance work are due to people and local authorities having requirements on compensation standards and support policies higher than the standards approved by competent authorities; The construction force of contractors is thin in many projects, so there is a lack of human resources, materials and construction equipment as committed. Many contractors can only meet about 50% of the required construction force, many construction equipment are too old to ensure capacity, and are constantly broken down; The financial work of contractors often does not meet the requirements, so sometimes they do not provide enough materials for construction (cement, steel, etc.). In general, construction contractors specializing in power sources are currently overloaded due to taking on many projects at the same time, not to mention projects invested by themselves. The acceptance, payment, and disbursement of projects are slow because contractors do not meet the requirements for completion and acceptance procedures. In addition, due to harsh weather, erratic storms and floods, and irregularities, it has caused difficulties in construction at hydropower projects built in remote areas, where material and spiritual conditions are poor and travel is difficult. This is also one of the factors affecting the progress of project implementation.

From the above issues, I choose: " Improving progress management work "

Implement Song Bung 4 hydropower project as a master's thesis in economics.

2. Overview

Author Tran Dinh Nhan's thesis: "Model of organization and management of construction investment projects in the Vietnam Electricity industry". The thesis studies the theory of organization and management of projects in general and construction investment project management in particular. The thesis has considered


Review and evaluate the project management model of Vietnam Electricity Group, thereby building an effective organizational model to manage the Group's construction investment projects.

Author Tran Uc's topic: "Project management at Da Nang Tien Phong Economic Development and Construction Joint Stock Company (Illustrated through the Hoi An City Continuing Education - Vocational Guidance Center Project). The research topic evaluates the project management activities of the Company and through the illustration of the Hoi An City Continuing Education - Vocational Guidance Center project, the topic synthesizes the theoretical basis of project management; analyzes the current situation and proposes basic solutions in terms of management in the process of organizing and implementing construction projects at Da Nang Tien Phong Economic Development and Construction Joint Stock Company.

3. Research purpose of the topic

Systematize the theoretical basis of project management and progress management of construction investment projects.

Correctly assess the current status of progress management of Song Bung 4 Hydropower Project and deeply analyze the monitoring and control of project implementation progress. Draw out the results, the issues that need to be solved and their causes.

Propose some solutions to improve the progress management of Song Bung 4 hydropower project based on the project implementation plan that has been and is being implemented.

4. Research object and scope

The research topic is about project implementation, focusing on researching and analyzing in depth the work of planning, progress management, monitoring & controlling project implementation progress and some other factors affecting the progress of Song Bung 4 hydropower project such as: bidding work, influence of parties participating in the project.

5. Research methods

5.1. General research methods


In implementing the research topic, the author uses dialectical materialism, theories of project management and other sciences to perceive, analyze and evaluate issues scientifically and objectively. This is also the basis of the methodology to apply specialized methods accurately in the research process of the topic.

5.2. Specific methods

- Information collection methods: The project collects a number of documents, papers, reports and existing research in Vietnam related to project implementation through various sources (Project Management Textbook, Construction Investment Project Management Textbook, Government Decrees, Circulars guiding the implementation of Decrees of Ministries, Specific Instructions of Vietnam Electricity Group, Asian Development Bank, domestic and international project management experts in Vietnam,...) to gain a common understanding of issues of interest and research tasks.

- Expert method: Interview and discuss with project management experts to obtain their experiences, comments and opinions on issues related to project implementation, especially project progress monitoring and evaluation, bidding and relationships with relevant parties involved in the project implementation process... in each specific situation at the Song Bung 4 Hydropower Project.

- Synthesis method: The topic synthesizes, analyzes and evaluates based on collected documents and information to give opinions on the implementation of the Song Bung 4 hydropower project, comments on the monitoring and control of the progress of the Song Bung 4 hydropower project; at the same time, proposes a number of solutions to improve the management of the progress of the Song Bung 4 hydropower project.

- The project used some specialized tools in project management such as: Gantt chart, milestone chart, earned value analysis (EVA), plan variation index (SPI) and used specialized software Microsoft Project to schedule the project...


6. Scientific and practical significance of the topic

The topic that the author is researching is highly practical, closely related to the current situation of a hydropower project under construction. Within the scope of the topic, it is not possible to mention all the problems that exist in a comprehensive manner in many areas of construction investment project management. However, within a certain framework, the topic has provided general solutions for project implementation and specified proposals to improve the progress management of the Song Bung 4 hydropower project and from there, practical experiences from this project will be drawn to apply to other projects that are being and will be implemented in Quang Nam province in particular and the Central region in general.


7. Structure of the topic

The topic is structured into 3 chapters:

Chapter 1: Theoretical basis of construction investment project progress management.

Chapter 2: Current status of progress management of Song Bung 4 hydropower project.

Chapter 3: Some solutions to improve the management of the progress of the Song Bung 4 hydropower project.