Cost Management Accounting at Tu Loc Joint Stock Company - 13


ACCOUNT DETAILS BOOK 622

Direct labor costs Project: Clubhouse Quarter 4, 2019


Unit: D



Date of entry

Document


Interpretation

Diary

steam


TKĐU

Number of occurrences


SH


NT

Page

book

STT

Current


In debt


Have

1

2

3

4

5

6

7

8

9




Surplus




-

-


10/19


PKT 96


10/19

Calculate the wages payable for the dining room item



334

5,430,120


10/19

PKT 96

10/19

Calculate salary deductions

for dining room category



338

3,626,078



October 30


PKT 118


October 30

Calculate the labor cost for garden and kitchen items.



334

10,150,900


October 30

PKT 118

October 30

Calculate salary deductions for garden items



338

4,735,462





………






12/31

PKT 256

12/31

Cost transfer

Raw materials into the cost price



154


39,158,333




Add the generated numbers




39,158,333

39,158,333




Final balance




-

-

Maybe you are interested!

Cost Management Accounting at Tu Loc Joint Stock Company - 13


The person who prepared the table (signature, full name)


Chief Accountant (signature, full name)

December 31, 2019 Director

(Signature, full name, seal)


ACCOUNT DETAILS BOOK 623

Construction machinery costs Project: Clubhouse Quarter 4, 2019


Unit: D



Date of entry

Document


Interpretation

Diary

steam

TKĐU

Number of occurrences


SH


NT

Page

book

STT

Current



In debt


Have

1

2

3

4

5

6

7

8

9




Surplus







10/13


Traffic Law 345


10/13


Forklift rental



331

2,800,000



10/15


Traffic Law 349


10/15


Hand drill



331

1,500,000





………






12/31

PKT257

12/31

Transferring construction machine costs into cost price

merit



154


7,324,540




Add the number of broadcasts

born




7,324,540

7,324,540




Final balance




-

-


The person who prepared the table (signature, full name)


Chief Accountant (signature, full name)

December 31, 2019 Director

(Signature, full name, seal)


ACCOUNT DETAILS BOOK 627

General production costs Project: Clubhouse Quarter 4, 2019


Unit: D



Date of entry

Document


Interpretation

Diary

steam

TKĐU

Number of occurrences


SH


NT

Page

book

STT

Current



In debt


Have

1

2

3

4

5

6

7

8

9




Surplus







10/13

Traffic Law

0134


10/13

Buy bread, no water to reward construction workers



331

770,000



10/14


PXK 01350


10/14

Export CCDC for

project




3,600,000



October 30


PKT120


October 30

Calculate salary payable in October for management workers



334

13,837,143



October 30


PKT120


October 30

Calculate salary deductions for management workers



338

1,357,013





………






12/31

PKT258

12/31

Cost transfer

SXC into the cost price



154


23,250,946




Add the generated numbers




23,250,946

23,250,946




Final balance




-

-


The person who prepared the table (signature, full name)


Chief Accountant (signature, full name)

December 31, 2019 Director

(Signature, full name, seal)


Service costing card

Project: Clubhouse

Quarter 4, 2019


Unit: D


Target

Total amount

Split by item

Ingredient,

material

Labor

direct

Test machine

labour

Production cost

A

1

2

3

4

5

1. Cost

Unfinished business at the beginning of the year

-

-

-

-

-

2. Cost

Production and business development

born in

129,220,149

60. 578,943

39,158,333

7,324,540

23,250,946

3. Price

service in kǶ

129,220,149

60. 578,943

39,158,333

7,324,540

23,250,946

4. Cost

Unfinished business at the end of the period

-

-

-

-

-



The person who prepared the table (signature, full name)


Chief Accountant (signature, full name)

December 31, 2019 Director

(Signature, full name, seal)

Unit: Tu Loc Joint Stock Company

Address: 55 Ngo 1, Kham Thien, Dong Da, Hanoi

ACCOUNT DETAILS BOOK 154

Work in progress costs Quarter 4, 2019


Unit: D



Date of entry

Document


Interpretation

Diary

steam

TKĐU

Number of occurrences


SH


NT

Page

book

STT

Current



In debt


Have

1

2

3

4

5

6

7

8

9




Surplus




820.230.123



11/30

PKT 125


11/30

Transfer and allocate production costs of Van Son restaurant company



627

23,770,000



12/31

PKT 256


12/31

Allocation and transfer of Clubhouse CT material costs



621

60. 578,943



12/31


PKT257


12/31

Allocate and transfer NCTT CT Clubhouse costs



622

39,158,333



12/31


PKT258


12/31

Transfer of construction machine costs to CT Clubhouse



623

7,324,540





………






12/31

PKT 261

12/31

Allocation and transfer of production costs

CT Clubhouse



627

23,250,946


12/31

PKT287

12/31

Cost of capital

Clubhouse



632


129,220,149




Add the generated numbers




1,266,897,200

1,834,456,520




Final balance




649,473,323

-


The person who prepared the table (signature, full name)


Chief Accountant (signature, full name)

December 31, 2019 Director

(Signature, full name, seal)




STT


Code


Employee name

Unit

Salary coefficient

Regional minimum wage

Wage

CB

Unit price

labor

1

N003

Craftsman level 3.5 7

Group I

Labour

2,355

3,250,000

7,653,750

294,375

2

N001

Level 4 7

Group I

Labour

2.55

3,250,000

8,287,500

318,750

3

N2004

Worker 4/7

Labour

2.55

3,250,000

8,287,500

318,750

4

N2005

Worker 5/7

Labour

3.01

3,250,000

9,782,500

376,250

5

N24.0001

Labor

2.5/7

Labour

1,995

3,250,000

6,483,750

249,375

6

N24.0005

Labor 3/7

Labour

2.16

3,250,000

7,020,000

270,000

7

N24.0008

Labor

3.5/7

Labour

2,355

3,250,000

7,653,750

294,375

Unit: Tu Loc Joint Stock Company

Project: …..

ACCEPTANCE RECORD OF COMPLETED CONSTRUCTION VOLUME

Date month year 2019 Construction team leader's full name:

Technical staff name: Pham Quang Thang - Technical staff Confirming completed construction volume in the quarter


STT

Job Description

Unit

Mass

Unit price

Total amount

1






2






3






4







Total






Construction team leader (signature, full name)

Technical staff (signature, full name)

decorate.


MATERIAL PRICE LIST

(Price does not include VAT)


Unit: VND

STT

The name of the word

Measure

Price

copper

1

Wire brush

female

4.5

2

Brush door panel

female

38

3

Three sticky

roll

4

4

Cloth bag

roll

4

5

Fabric insulation bag

roll

10

6

4 channel flashing remote control

bug

200

7

The controller flashes 2-3 times.

bug

150

8

1.2m tube light

female

10

9

Incandescent light bulb

female

3,636

10

Bolt M18x250

female

7

11

Sand poured into concrete

m3

306,364

12

S-shaped lamp post, L 2.8m

bug

300

13

S-shaped, L-shaped lamp arm 3.2m

bug

360

14

Lamp holder D60, L 2.8m

bug

300

15

Lampshade D60, L 3.2m

bug

360

16

Lamp holder D60, L 3.6m

bug

390

17

Lamp holder D60, L 3.8m

bug

420

18

Lamp holder D60, L 4.4m

bug

480

19

Lamp D60, L 4m

bug

450

20

Lamp need D60, L 6m

bug

600

21

Need filament lamp D48, L 2.5m

bug

240

22

Need filament lamp D48, L 1.5m

bug

120

23

Need filament lamp D48, L 2.5m

bug

200

24

Need filament lamp D48, L 2m

bug

150

25

PVC sheathed copper cable, 4 cores (3x14+1x11)

m

180

26

PVC sheathed copper cable, 4 cores (3x22+1x11)

m

255.9

27

Cable cross section 26-50mm2

m

94.8

28

Cable cross section 6-25mm2

m

41.2